|
Triumphs
and Trials
- A First Monolithic Dome Construction
Yet they don't regret the experience. In fact, they're anticipating building an adjoining dome in 2002. There are two reasons for that enthusiasm. Erling gives the first: "Our dome construction process took two years of weekends, holidays and vacations - more than 3,000 hours. But we're very proud of our dome home accomplishments and savings. We often tell others that we pioneered the first Monolithic Dome home in Virginia." Erling and Barbara had each worked in the construction industry. They knew a lot about conventional construction when they first surfed onto the Monolithic Dome website that immediately caught their interest. Barbara says, "We wanted a home that would provide protection and efficiencies." They ordered and reviewed more information, then participated in the April 1998 MDI Workshop. Their search for financing became their first trial. After purchasing 13 wooded acres with springs and a stream, the Rosholdts, armed with dome plans and detailed cost quotes from all trades, contacted 11 lenders. "That was a mistake," Barbara says. "We wasted six months trying for normal financing. We were turned down by all 11 lenders." "We used that money for site work, foundation, Airform, foam insulation, rebar and concrete," Erling says. "Then each future, paycheck-to-be-earned became our construction fund. That's sweat equity." But the Rosholdts' decision to have their foundation poured before ordering their Airform turned into a triumph. They had placed two inches of polystyrene insulation board vertically between the foundation and ground and one inch on the slab area over the plastic vapor barrier for the slab hot water hydronic system. A local concrete company then poured and finished the slab and foundation together. Erling says, "I wanted the strength from a monolithic pour so that any ground shifting would move the structure in unison. like a floating slab." During the eight weeks that it took the Airform to arrive, the Rosholdts built the airlock entrance, bought a commercial fan blower, installed a temporary outside electric service panel and began a begging and bribing campaign. "We desperately needed help to move and anchor the heavy Airform," Barbara says. They got the help, connected the blower and airlock and turned on the fan. Nothing happened! "Finally we found the membrane at the blower port that we needed to cut out," Barbara says. "Fourteen minutes later our dome was inflated!" Before spraying, Barbara duct taped the front of electrical boxes and door and window frames. Although the tape protected surfaces that didn't require spraying, it proved hard to remove once it got covered with foam and concrete. When Erling ordered their concrete, he specified, "No aggregate," but the concrete truckers hadn't cleaned the drum of aggregate from another delivery. "We were given extra, no-charge concrete," Erling says, "but we still had unproductive equipment down time. First dumping the concrete through a screen on top of the pump hopper would have prevented this."
For more information about photographer Andrew Shurtleff, click here! Phase II (Submitted by Rosholdts on September 24, 2003)We obtained a first dome mortgage in 2002 after the lender saw how nice and conventionally livable it finished out. This helped us consolidate our debts and gave seed money to start the next two (adjoining) 28 ft and 40 ft domes. The Winter of 2002 was mild enough to work outside weekends preparing the foundation site and slab concrete formwork. The foundation slab was finished and Airform ordered in April 2003. We set up our EHP1500 pump, Inflator fan, airlock, inflated Airform in July, and then set up steel door and window frames inside. The spraying of foam insulation during our mid-August "vacation" was very hot work. Once the insulation was finished, the interior insulated "shade" was much cooler. Our friends once again helped us with the rebar hanging, while we mounted electrical conduit and outlet boxes. We hired two expert shotcrete sprayers from Monolithic Dome Institute and flew them to Virginia. About sixty yards of ready mix were sprayed for the two domes. Before the last sand coat, the fan was turned off and we removed the airlock, cleaning up the rebound with a Bobcat, using the framed garage door opening. From August 2002 to September 2003, we continued to work weekends framing the walls, installing plumbing lines, electrical wiring, and HVAC ductwork. Contractors installed windows, drywall and flooring. We finished painting and installing fixtures in September 2003, leaving only a few "punch list" items to complete for final inspection. |
||||||||||||